Cenovus Energy (NL)
Project SummaryThe power generation system for the SeaRose FPSO (floating, production storage and offloading vessel) comprises three dual fuel turbine driven generators, which provide power to the process and utility equipment. The SeaRose currently runs three of the main power generators with a partial load. This study will identify the necessary modifications to increase the energy efficiency of the SeaRose power generation system with a target of reliably operating with two main power generators. This could result in a significant reduction in associated greenhouse gas (GHG) emissions by removing the requirement to run the third main power generator. The study will determine the technical and commercial feasibility of the options and provide a recommendation on the path forward to achieve a GHG reduction. www.cenovus.com
|
Scope:Operational Optimization
Emission Source:Power Generation
Project Type:Related Science Activity
Operational Area:Production
Funding Amount:$505,605 |